updates from friday, 12/11/09 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Update: Guys there today finishing upper wall for possible pour on Thursday. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1/27/2010-1/28/2010. a(measurements for flooring kitchen - 8 x 10; bathroom #1 3 x 10 and Bathroom #2 8 x 4. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Today the guys are working on expanding the shower area, which is done and flooring. The shower enclosure will come after plumbing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3/16/2010. Electric complete. waiting on Elec. Co. Water Main on and job almost complete |
|
|
|
|
|
|
|
|
|
|
|
|
|